Baltic Power

In 2023, JDR signed a contract for the development of the Baltic Power offshore wind farm in Poland. The project involves the design, manufacture, and installation of 340 km of both onshore and subsea cables. Located 23 km off the Polish coast, the farm will cover approximately 130 square kilometers and will feature 76 wind turbines, each with a capacity of 15 MW. Once completed in 2026, the farm will generate a total capacity of 1.2 GW, enough to power over 1.5 million households with clean energy. The cables to be produced and installed include 230 kV onshore export cables and inter-array cable components, which will be produced at the Bydgoszcz manufacturing plant. The production and delivery of all subsea cables are scheduled for the end of 2025, contributing to the further development of renewable energy in Poland.