Formosa 1 is Taiwan's first commercial-scale offshore wind energy project, located approximately 6 km off the western coast of Miaoli in the Taiwan Strait. As part of the project, 21 km of inter-array cables, 13 km of export cable, and 16 km of onshore cables were supplied to transmit energy from the wind turbines to the shore. In 2020, JDR and the Bydgoszcz facility produced and delivered the required cables, along with providing accessories, cable installation, equipment assembly, and post-installation support, carried out by a team of 26 technicians on the offshore turbine platforms.

Formosa 1 is a key milestone in the development of the wind energy sector in Taiwan, and it is the first project in the region to enable the commercial production of offshore wind energy. The project achieved a total capacity of 120 MW upon completion of its second phase.